The following information, except where noted, is contained in the Resolution of the Henry County Board of Commissioners authorizing execution of the 2007 SPLOST Intergovernmental Agreement.   It is not posted publicly - this is an exclusive!

 

* The IG lists budget costs for Capital projects the COUNTY will fund.   Each City lists a general category for each type of funding.

CAPITAL BUILDINGS (NEW CONSTRUCTION)

Senior Center - Hampton
Senior Center - Locust Grove                         Senior Centers:                                                   $4,590,000
Domestic Violence Shelter                              Social Services Facilities (Haven House): $2,142,000

Correctional Facility (phase II)                                                                                                     $10,000,000
Parking Deck - Courthouse Area                                                                                                   $4,500,000
Civic Center /Performing Arts Center                                                                                        $7,000,000

CAPITAL BUILDINGS (PUBLIC SAFETY)

Replacement Fire Stations:                                                                                                                           
Station # 2 - Locust Grove                                                                                                              $1,500,000
Station # 8 - Flippen Road                                                                                                               $1,500,000
Station # 9 - City of Stockbridge                                                                                                   $2,700,000
Emergency Operations Center                                                                                                      $1,400,000

 

NOT ON THE COUNTY WEBSITE:

Recreational Centers                                                                                                  $6,500,000

Recreational Improvements                                                                                   $4,750,000

Land Acquisition                                                                                                           $18,023,000

MAJOR TRANSPORTATION PROJECTS

* Cost estimates for Transportation projects are contained in spreadsheets produced by and for the Board of Commissioners as work product.  Although the information was not created, prepared or derived in executive session, the spreadsheets are not published as part of the ballot or project lists.

 

District 1


Major Transporation Projects
Bill Gardner Parkway (I-75 to SR 155)                                                                                       $4,000,000       

Intersections
Bethany Road @ SR 81                                                                                                                    $800,000
Harris Drive @ SR 42                                                                                                                      $1,400,000
Kingsmill @ SR 42                                                                                                                            $2,200,000
Keys Ferry Road @ SR 81                                                                                                                $900,000
Mt Bethel Road @ SR 81                                                                                                                  $1,000,000

Dirt Road Paving
Mackey Road (Keys Ferry Road to Stallworth Road)                                                              $1,400,000
Stallsworth Road (Mackey Road to Sandy Ridge Road)                                                          $1,400,000
Collins Way (Peeksville Road to Henry County Water                                                          $1,200,000

and Sewer Authority property)
Collins Drive (Locust Grove Griffin Road to Henry County Water                                    $1,000,000

and Sewer Authority property)

Peeksville Road (Old Jackson Road to New Hope Road (ROW Only)                                   $500,000
South Bethany Road (Jackson Street to Price Drive West )                                                  $2,200,000
New Hope Road (EOP to Peeksville Road)                                                                                   $1,800,000
Harris Drive (Leguin Mill Road to South Bethany Road)                                                      $2,000,000
South Bethany Road (Coan Drive to Philadelphia Drive)                                                     $2,300,000


NOT PUBLISHED           Contingency/ Second Tier Projects to be addressed

if revenues exceed $300 million

 

Dirt Road Paving

Frog                                                                                                                                                       $2,062,000

Lester Mill (Bill Gardner to Indian Creek)                                                                                 $3,300,000

Lester Mill (Indian Creek to LG Griffin Rd)                                                                                $2,500,000

 

District II


Major Transportation Projects
Bill Gardner Parkway Design and ROW                                                                                     $2,000,000
Western Corridor Phase I                                                                                                                $2,581,000
Hudson Bridge Road                                                                                                                         $5,860,000
Parallel Collector                                               (* Access Road, West of I-75)                          $2,000,000
Hwy 138 Median Landscaping                                                                                                     $20,000

Intersections
Old Highway 3 @ SR 81                                                                                                                  $1,910,000
Blackhall Road @ Jodeco Road                                                                                                      $1,500.000

Dirt Road Paving                                                                                                                                              
Oakland Road                                                                                                                                     $2,200,000
Pullin Road                                                                                                                                          $2,400,000
Simpson Mill Road                                                                                                                             $1,800,000

Bridges                                                                                                                                                  $700,000

Resurfacing/Federal/State & Private Joint Ventures Projects                                            $1,129,000

 

NOT PUBLISHED           Contingency/ Second Tier Projects to be addressed

if revenues exceed $300 million

 

Major Transportation Projects
Western Corridor Phase II                                              

 

Intersections

Walker Rd @ SR 155                                         (* Henry DOT project in 2007)   

Hampton Locust Grove Rd @ Rocky Creek Rd

New Morn @ SR 81

Mill Road @ SR 81

 

Dirt Road Paving              

Fears Road


District III


Major Transportation Projects                                                                                                     
Campground Road Extension                                                                                                        $5,310,907
East Lake Road Extension Phase II                                                                                                $1,143,000
McDonough Parkway Jonesboro to 42                                                                                        $1,215,000
Racetrack Road Extenstion                                                                                                             $520,000
McDonough Parkway SR 42 to Sr 155                                                                                        $1,000,000

Intersections
Airline @ SR 20                                                                                                                                 $1,393,000
Bethany @ SR 81                                                                                                                              $799,000
Lake Dow @ SR 81                                                                                                                             $1,l272,000
Keys Ferry @ SR 81                                                                                                                          $426,433
Crumbley @ SR 155                                                                                                                         $1,478,160


Dirt Road Paving
Elliot Road                                                                                                                                           $ 0.00

Bridges                                                                                                                                                  $700,000

Resurfacing                                                                                                                                         $1,000,000

 

** Item listed on Cost Analysis Spreadsheet, not found at County website

 

McDonough Pool                                                                                                                $500,000


District IV


Major Transportation
Eagles Landing Parkway                                                                                                                **
East Lake Road Extension Phase II                                                                                                $127,000
Rock Quarry Road Bridge over Norfolk Southern Railroad                                                 
Rock Quarry Road Widening (Eagles Landing Parkway to SR 138)
Rock Quarry Road Extension from SR 138 to

East Atlanta @ Valley Hill (Design Only)

Walter Way Extension from SR 138 to SR 42 (Design Only)

 

** It must be noted that District IV funds were initially reduced by about $15 million for

Eagles Landing Parkway, considered a SPLOST II project.  Also, about $4.9 million was

dedicated from District V funds. 


Intersections
East Atlanta Road/Mays Road/Stagecoach Road                                                                     $1,703,062
Hemphill Road @ SR 138                                                                                                                $1,200,000
Banks Road @ Rock Quarry Road                                                                                                 $1,600,000
Moseley Park Entrance @ Miller's Mill Road


** Item listed on Cost Analysis Spreadsheet, not found at County website

Davis Drive @ SR 42                                                                                        $1,692,160


Bridges                                                                                                                                                  $700,000

Resurfacing                                                                                                                                         $2,000,000

 

District V


Major Transportation Projects
Fairview Road Widening (Cook Road to Thurman Road)                                                      $12,255,000
Anvil Block Road Widening                                                                                                            $1,350,000

Intersections
East Atlanta Road @ Panola Road                                                                                                $1,450,000
East Atlanta Road @ Thurman Road                                                                                          $1,450,000
Hemphill Road @ SR 138                                (* Not on Cost Analysis Spreadsheet)

Bridges                                                                                                                                                  $700,000
Resurfacing                                                                                                                                         $1,000,000

 

NOT PUBLISHED           Contingency/ Second Tier Projects to be addressed

if revenues exceed $300 million

Intersections

East Atlanta @ Rex Road

Kelleytown @ Airline

Old Conyers @ Flat Shoals Church

Scarborough @ Panola

Austin @ Hearn Realignment

Flt Rock @ Flakes Mill

East Atlanta/Mays/Stagecoach

 

 


The following information, except where noted, is contained in the Resolution of the Henry County Board of Commissioners authorizing execution of the 2007 SPLOST Intergovernmental Agreement.  

 

* The IG lists budget costs for Capital projects the COUNTY will fund.   Each City lists a general category for each type of funding.

 

EXHIBIT “B”

City of Hampton

 

If the 2007 SPLOST Referendum is approved by the voters of Henry County, the City of Hampton anticipates it will expend the funds as details below.  Expenditures for any of the projects described below may also include the repayment of public debt or other obligations of the City of Hampton incurred for or associated with such project.

 

Project                                                                                                                 Estimated Cost

 

Roads, Bridges, Sidewalks                                                                               $1,300,000

Public Safety Facilities and Equipment                                                     $3,750,000

Public Works Facilities and Equipment                                                      $1,450,000

Construction and Renovation of Municipal Buildings                           $30,000

Parks and Recreation Facilities                                                                     $270,000

Community Development Facilities                                                           $350,000

Acquisition of Property for Public Use                                                         $500,000

               

                                                                                Total:                                     $7,650,000

 

 

EXHIBIT “C”

City of Locust Grove

 

If the 2007 SPLOST Referendum is approved by the voters of Henry County, the City of Locust Grove anticipates it will expend the funds as details below.  Expenditures for any of the projects described below may also include the repayment of public debt or other obligations of the City of Locust Grove incurred for or associated with such project.

 

Project                                                                                                                 Estimated Cost

 

Roads, Bridges, Sidewalks and Transportation Facilities                      $2,900,000

Public Safety Facilities and Equipment                                                     $2,000,000

Construction and Renovation of Municipal Buildings                           $750,000

Parks and Recreation Facilities                                                                     $500,000

Acquisition of Property for Public Use                                                         $1,500,000

               

                                                                                Total:                                     $7,650,000

 

 

EXHIBIT “D”

City of McDonough

 

If the 2007 SPLOST Referendum is approved by the voters of Henry County, the City of McDonough anticipates it will expend the funds as details below.  Expenditures for any of the projects described below may also include the repayment of public debt or other obligations of the City of McDonough incurred for or associated with such project.

 

Project                                                                                                                 Estimated Cost

 

Roads, Bridges, Sidewalks and Transportation Facilities                      $2,500,000

Public Safety Facilities and Equipment                                                     $8,342,500

Public Works Facilities and Equipment                                                      $3,250,000

Community Development Facilities                                                           $250,000

Alexander Park and other Park and Recreation Facilities                    $7,000,000

Repayment of Public Debt Associated with the Above Projects

Or Retirement of Previously Incurred General Obligation Debt        $5,500,000

               

                                                                                Total:                                     $26,842,000

 

 

 

EXHIBIT “E”

City of Stockbridge

 

If the 2007 SPLOST Referendum is approved by the voters of Henry County, the City of Stockbridge anticipates it will expend the funds as details below.  Expenditures for any of the projects described below may also include the repayment of public debt or other obligations of the City of Stockbridge incurred for or associated with such project.

 

Project                                                                                                                 Estimated Cost

 

Roads, Bridges, Sidewalks  and Transportation Facilities                     $3,060,000

Public Safety Facilities and Equipment                                                     $2,000,000

Public Works Facilities and Equipment                                                      $17,097,500

Construction and Renovation of Municipal Buildings                           $10,700,000

               

                                                                                Total:                                     $32,857,500